×

UPSC Courses

DNA banner

DAILY NEWS ANALYSIS

GS-III :
  • 19 May, 2020

  • 10 Min Read

A jolt to national energy security

A jolt to national energy security

By,Sudha Mahalingam, Tejal Kanitkar and R. Srikanth are, respectively, Raja Ramanna Chair Professor, Associate Professor and Dean in the Energy and Environment Program at the National Institute of Advanced Studies, Bengaluru

Introduction

The government’s proposal for reform of power tariff policy , is of a piece with the recent comprehensive proposal to amend the Electricity Act 2003; put together, they erode the concurrent status accorded to electricity in the Constitution.

If implemented, they will not only weaken the control of States over an industry supplying a basic human necessity such as electricity but also arm the Centre with a pincer-like weapon which could choke the distribution utilities/companies (DISCOM) and jeopardise the country’s energy security.

DISCOM troubles

These proposals have to be seen in the context of a continuing centralisation of control over the sector whose main impact in the last 25 years has been to drive up the cost of power purchase to 80% of the total costs of State DISCOMs.

At the core of DISCOM woes is the two-part tariff policy, mandated by the Ministry of Power in the 1990s at the behest of the World Bank.

As more private developers came forward to invest in generation, DISCOMs were required to sign long-term power purchase agreements (PPA), committing to pay a fixed cost to the power generator, irrespective of whether the State draws the power or not, and a variable charge for fuel when it does.

The PPAs signed by DISCOMs were based on over-optimistic projection of power demand estimated by the Central Electricity Authority (CEA), a central agency.

The 18th Electric Power Survey (EPS) overestimated peak electricity demand for 2019-2020 by 70 GW.

The 19th EPS published in 2017, by 25 GW, both pre-Covid 19.

In the event, DISCOMs locked into long-term contracts end up servicing perpetual fixed costs for power not drawn.

NTPC Limited’s Kudgi, in Karnataka, alone received ?4,800 crore as idle fixed costs during 2018-19, operating at a plant load factor of only 22%.

Due to the CEA’s overestimates, the all-India plant load factor of coal power plants is at an abysmal 56% even before COVID-19.

Factor of renewable energy

From 2010, solar and wind power plants were declared as “must-run”, requiring DISCOMs to absorb all renewable power as long as there was sun or wind, in excess of mandatory renewable purchase obligations.

This means backing down thermal generation to accommodate all available green power, entailing further idle fixed costs payable on account of two-part tariff PPAs.

Second, power demand peaks after sunset. In the absence of viable storage, every megawatt of renewable power requires twice as much spinning reserves to keep lights on after sunset.

DISCOMs, especially in the southern region, have had to integrate large volumes of infirm power, mostly from solar and wind energy plants which enjoy must-run status irrespective of their high tariffs (?5/kwh in Karnataka and ?6/kwh in Tamil Nadu for solar power) even as the demand growth envisaged in the 18th EPS failed to materialise.

Third, in 2015 the Centre announced an ambitious target of 175 gigawatts of renewable power by 2022, offering a slew of concessions to renewable energy developers, and aggravating the burden of DISCOMs. Incidentally, China benefited by as much as $13 billion in the last five years from India’s solar panel imports.

Electricity Bill,2020

It is against this backdrop that we must examine the proposals in the Electricity Act 2020.

First, the amendment proposes sub-franchisees, presumably private, in an attempt to usher in markets through the back door.

Going by past privatisation experiments, private sub-franchisees are likely to cherry-pick the more profitable segments of the DISCOM’s jurisdiction.

The Electricity Bill 2020 containing the proposed amendments is silent on whether a private sub-franchisee would be required to buy the expensive power (averaging out the idle fixed costs) from the DISCOM or procure cheaper power directly from power exchanges.

If it is the first, the gains from the move are doubtful since the room for efficiency improvements is rather restricted in the already profitable regions attractive to sub-franchisees. If it is the second, DISCOMs will then be saddled with costly power purchase from locked-in PPAs and fewer profitable areas from which to recover it.

Second, the amendment proposes even greater concessions to renewable power developers, with its cascading impact on idling fixed charges, impacting the viability of DISCOMs even more.

Third, and the most controversial amendment proposed, seeks to eliminate in one stroke, the cross-subsidies in retail power tariff.

This means each consumer category would be charged what it costs to service that category.

Rural consumers requiring long lines and numerous step-down transformers and the attendant higher line losses will pay the steepest tariffs.

Disingenuously, the proposed amendments envisage that State governments will directly subsidise whichever category they want to, through direct benefit transfers.

Eliminating cross-subsidies in one stroke when State governments are already struggling with direct power subsidies is bound to be ruinous to their finances, not to mention the myriad problems with Direct Benefit Transfer.

Fourth, State regulators will henceforth be appointed by a central selection committee, , jeopardising not only regulatory autonomy and independence but also the concurrent status of the electricity sector.

Finally, the establishment of a centralised Electricity Contract Enforcement Authority whose members and chairman will again be selected by the same selection committee referred to above.

The power to adjudicate upon disputes relating to contracts will be taken away from State Electricity Regulatory Commissions and vested in this new authority, ostensibly to protect and foster the sanctity of contracts.

When the country is reeling under the economic impact of the novel coronavirus crisis, the Electricity Bill 2020 is indeed a disingenuous document drafted to shift the burden imposed by the short-sighted policies of the Centre onto hapless States, with serious consequences for the nation’s energy security.

Source: TH


Geopolitical Significance of Ports

Geopolitical Significance of Ports (IR)  Act as geopolitical assets: Ports enhance the projection of strategic reach, which helps strengthen the country’s control over important sea and energy supply routes.  E.g. Indian Navy’s staging base at Agalega Islands will enable marine patrols

SPACE VEHICLE - PSLV & GSLV - Space ORBITS

SPACE VEHICLE - PSLV & GSLV - Space ORBITS (S&T) GS PAPER-3 India has one of the world's most effective and active space programmes, with a diverse set of missions and accomplishments in the space sector. The Indian Space Research Organisation (ISRO) is India's primary space agency located in Bangalore. It has made sign

Pradhan Mantri Suryodaya Yojana

Recently, Prime Minister announced Pradhan Mantri Suryodaya Yojana under which 1 crore households will get rooftop solar power systems. India’s Status of Current Solar Capacity India currently stands at 4th place globally in solar power capacity. As per Ministry of New an

Foreign Contribution Regulation Act (FCRA)- NGO 

The Foreign Contribution Regulation Act, 2010 (FCRA) registration of two prominent non-governmental organisations (NGOs) — Centre for Policy Research (CPR) and World Vision India (WVI) have been cancelled this month. What is FCRA? Key provisions of FCRA, 2010 Key aspects Description

Voice clone-AI

Voice clone fraud has been on the rise in India. AI voice cloning – It is the process of creating a synthetic replica of a person’s voice through machine learning and speech synthesis technology.It is called as voice deepfakesor audio deepfakes. Objective – To achieve a high level of na

Toppers

Search By Date

Newsletter Subscription
SMS Alerts

Important Links

UPSC GS Mains Crash Course - RAW Prelims Answer Key 2024